Division Street Tank and Booster Pump Station

Location:

Mt. Vernon, WA

Project Overview:

This project included the construction of a new 6 million gallon reservoir and booster pumping station to replace the aged and undersized existing system. The new station and system is capable of the state required 2 day supply of water to its service area. The tank was built with prestressed concrete walls, a key element in supporting the height of the tank. This type of construction is not typically seen in the northern Puget Sound region.

Services Provided:

GeoTest provided special inspection and testing services throughout construction. These services included inspection and testing of mass grading, reinforced concrete inspection and testing, prestressed concrete testing, structural steel inspection and adhesive anchor inspection

Owner:

Skagit PUD No. 1

Project Cost:

$14.4 Million

Additional Services Provided:

Environmental Consulting, Soil Sampling, Concrete Testing

Contact Geotest

Geotest welcomes the opportunity to become a part of your team and build the success of your company. We provide Construction Special Inspection and Materials Testing Services throughout Northwest Washington. Our Geotechnical Engineering Department and Environmental team can provide services in Washington State and Oregon.

  • This field is for validation purposes and should be left unchanged.